Mohammadpur Power Station |
3 X 3.1 |
RMU work of Mohammadpur Power Station is completed on 21/07/2013. |
Pathri Power Station |
3 X 6.8 MW |
RMU work of Pathri Power Station is completed on 30/11/2014. |
Khatima Power Station |
3 X 13.8MW |
RMU Works (Electro-mechanical & Hydro-Mechanical) Completed on 08.09.2016 |
Tiloth HEP (MB-1) |
3 X 30 |
RMU works of Tiloth HEP is completed on 08.09.2022 |
Dhalipur HEP |
3 X 17 |
RMU works of Dhalipur HEP is completed on 07.10.2023 |
Dhakrani HEP |
3 X 11.25 |
RMU works are in progress and expected to be completed on 31.05.2026 |
Chilla HEP |
4 X 36 |
Agreement Executed RM&U in Jan 2020. Reverse engineering, model test, cranes refurbishment, major design activities and manufacturing of DT one and runner chember completed. 1st Unit has been handed over to M/s BHEL for RMU Works on 07.11.2024. RMU is expected to be completed on 31/10/2027 |
Kulhal HEP |
3 X 10 |
Appeal has been disposed off by the Hon'ble Appellate Tribunal of Electricity, New Delhi vide order dated 04.09.2024 with the direction to move petition afresh based on fresh DPR prepared on the current requirements of RMU |
Ramganga HEP |
3 X 66 |
Appeal has been disposed off by the Hon'ble Appellate Tribunal of Electricity, New Delhi vide order dated 04.09.2024 with the direction to move petition afresh based on fresh DPR prepared on the current requirements of RMU |