Mohammadpur Power Station |
3 X 3.1 |
RMU work of Mohammadpur Power Station is completed on 21/07/2013. |
Pathri Power Station |
3 X 6.8 MW |
RMU work of Pathri Power Station is completed on 30/08/2014. |
Khatima Power Station |
3 X 13.8MW |
RMU Works ( Electro-mechanical & Hydro-Mechanical) Completed on 26.09.2016 |
Tiloth (MB-1) |
3 X 30 |
RMU Contract Agreement signed on 14.12.2016. RMU of Machine no. 1 ( First Unit under RMU) stared on 12.12.2018 and completed on 17.04.2020
RMU of Machine no. 3 (Second Unit under RMU) is under progress. |
Dhalipur HEP |
3 X 17 |
Agreement executed for M&U in April 2017. Reverse Engineering of one unit completed. Design and Engineering Works are in progress. The M&U is scheduled to be completed by June 2021. |
Dhakrani HEP |
3 X 11.25 |
Financial Evaluation of bids is in progress. |
Chilla HEP |
4 X 36 |
Agreement Executed RM&U in Jan 2020. The RM&U is Scheduled to be completed by July 2024. |
Kulhal HEP |
3 X 10 |
Hon’ble UERC has not given approval of RMU. Matter is pending with Hon’ble APTEL for considering approval of RMU. |
Ramganga HEP |
3 X 66 |
Hon’ble UERC has not given approval of RMU. Matter is pending with Hon’ble APTEL for considering approval of RMU. |